Hey Church!
We have another great update on our building project! The soil compaction tests for the backfill around the sewer lines all came back great. That's an important step forward, and we're thankful to see things continuing to move in the right direction!
One small delay: the additional fill dirt and time needed to meet the required compaction standards have pushed back the completion of the north road. We appreciate everyone's continued patience as the crew makes sure everything is done properly.
Looking ahead, surveyors will be onsite this week marking the building corners in preparation for digging the foundation footings. Things are starting to get exciting as we get closer to seeing the foundation take shape!
The team is working hard to get the foundation dug and poured before winter sets in. There's still work to do, but we're pushing forward and making good progress!
Thanks for continuing to be patient and excited with us as this project moves along. Have a great week, Church, and we'll see you Sunday!